Upload the schedule
North Campus · Phase 2 · monthly update, October
›PROJECT North Campus · Phase 2
›TASK 2,418 activities
›TASKPRED 3,906 logic links
›CALENDAR 6 calendars, 2 with night shifts
!Open ends 12 activities without a successor
›Critical 214 activities, float ≤ 0
›Key dates 7 found
✓Ready for a delay
Work breakdownActivities
- North Campus · Phase 22,418
- Site and civils312
- Energy centre286
- Hall 1874
- Hall 2904
- Electrical301
- Mechanical342
- Commissioning L1 to L5261
- Handover44
Describe the delay
New delay event · TIA-007
Delay eventDraft
- Event
- Late delivery, CRAH units
- Scope
- 10 of 20 units · Hall 2
- Late by
- 15 working days
- New date
- Deliveries from 26 Jan
- Source
- Supplier letter, 2 Oct, p. 1
Linked activities4
A2140Deliver CRAH units, Hall 2A2145Set CRAH units, Hall 2A2210Chilled water connectionsA2300Mechanical commissioning (L3)The real impact
TIA-007 · delay inserted into Rev 14 · data date 14 Oct
A2140Deliver CRAH unitsA2145Set CRAH unitsA2210Chilled water connectionsA2230Electrical terminationsA2300Mechanical commissioning L3A2350Fire systems testA2410Integrated systems test L5MS050EnergisationMS110Hall 1 ready for serviceMS210Hall 2 ready for serviceMS900Practical handoverKey datesworking days
| Key date | Planned | Now | Δ |
|---|---|---|---|
| Energisation | 12 Jan | 12 Jan | 0 |
| Hall 1 ready | 2 Mar | 2 Mar | 0 |
| Hall 2 ready | 16 Mar | 10 Apr | 0 |
| Handover | 30 Mar | 24 Apr | 0 |
Driving path5 links
A2140Deliver CRAH unitsA2145Set CRAH unitsA2210Chilled water connectionsA2300Mechanical commissioningA2410Integrated systems testMS900Practical handover
Options, tested
Every recovery the logic allows, tested against your calendars, crews and constraints
- Recovers
- 12 days
- Handover
- 8 Apr+7
- Cost
- €12,000
- Risk
- Medium
Needs: the fit-out crew moves to Hall 1 for two weeks.
Choose- Recovers
- 17 days
- Handover
- 1 Apr+2
- Cost
- €60,000
- Risk
- Low
Needs: the commissioning agent on Saturdays for five weekends.
Choose- Recovers
- 17 days
- Handover
- 1 Apr+2
- Cost
- €18,000
- Risk
- Medium
Needs: the client agrees to take Hall 1 first.
ChooseThe paperwork, done
Option 2, chosen by the project lead on 22 Oct · 4 documents
Generated from the impacted schedule and the chosen option.
Time impact statement
Late delivery of CRAH units, Hall 2
1 Summary
Late delivery of 10 of 20 CRAH units for Hall 2 delays practical handover by 19 working days. With the chosen recovery, weekend shifts for mechanical commissioning, the delay falls to 2 working days, at an estimated cost of €60,000.
2 Impact on key dates
| Key date | Planned | Impacted | Recovered |
|---|---|---|---|
| Energisation | 12 Jan | 12 Jan | 12 Jan |
| Hall 1 ready for service | 2 Mar | 2 Mar | 2 Mar |
| Hall 2 ready for service | 16 Mar | 10 Apr | 18 Mar |
| Practical handover | 30 Mar | 24 Apr | 1 Apr |
3 Delay fragnet
4 Recovery
- Weekend shifts for mechanical commissioning, five Saturdays.
- Commissioning agent confirmed by 30 Oct.
- Cost about €60,000, from project contingency.
5 Activities affected
| Activity | Planned finish | Impacted | Δ |
|---|---|---|---|
| A2140 Deliver CRAH units | 9 Jan | 30 Jan | +15 |
| A2145 Set CRAH units | 23 Jan | 19 Feb | +19 |
| A2210 Chilled water connections | 6 Feb | 5 Mar | +19 |
| A2300 Mechanical commissioning | 20 Feb | 19 Mar | +19 |
| A2410 Integrated systems test | 13 Mar | 9 Apr | +19 |
6 Method
The delay was inserted as a fragnet into the schedule current at the data date and the schedule was recalculated. Recovery options were tested against the same logic, calendars and constraints.
Send to client
Please find attached our time impact statement for the late CRAH delivery in Hall 2, the recovery we have chosen and the updated schedule.
Figures by role
The same decision, seen by two people
Option costs · TIA-007Euro
| Option | Recovers | Handover | Cost | From contingency |
|---|---|---|---|---|
| 1 Re-sequence Hall 2 fit-out | 12 days | 8 Apr | €12,000 | €12,000 |
| 2 Weekend commissioning shifts | 17 days | 1 Apr | €60,000 | €60,000 |
| 3 Commission Hall 1 first | 17 days | 1 Apr | €18,000 | €18,000 |
Project contingency
€1,200,000Who sees budget and contingency